BIM SUPPORT FOR RECONSTRUCTION OF THE BUILDING COMPLEX
To improve the quality of the issued documentation, IM Consult has undertaken full BIM support for the reconstruction of buildings at the Moscow Gate. This allowed the customer to get a complete picture of the upcoming work, as well as the ability to get the exact cost of reconstruction and choose the most optimal calendar and network schedule.

Task: Modeling, collision search and creation of a single database of information about all reconstructed objects
6 |
30 000 |
>4 000 |
_______________________________ | _______________________________ | _______________________________ |
Buildings fully modeled | The total area of all objects | Found more than 4000 collisions between project and fact |
About the project
To improve the quality of the issued documentation, IM Consult undertook full BIM support for the reconstruction of buildings at the Moscow Gate. This allowed the customer to get a complete picture of the upcoming work, as well as the ability to get the exact cost of reconstruction and choose the most optimal calendar and network schedule.
Initial data
Combining new and old technologies - dimensional drawings and point cloud.
Point cloud
A modern format for collecting baseline information. It allows you to measure the entire surrounding space, eliminating the possibility of inaccurate measurement or a missing element. To carry out such work, you need special equipment and skills. If you need to perform laser scanning, you can contact our partners from veso.pro.

Dimensional drawings
This data format makes it possible to measure linear dimensions at short distances without special tools, but the error of this method grows with each measurement. In this project, all measurements were made in this way. But measuring the facade with a tape measure is a difficult task, and it was measured with a laser scanner.
What was done?
![]() | Modeling interiors on flat plans |
Raising the model according to the drawings with the release of a three-dimensional model of the internal space of the building. | |
![]() | Facade reengineering |
The building facades were obtained from the point clouds for calculating the amount of work. | |
![]() | Project coordination |
Creation of a generalized file with all buildings for analyzing the situational plan and working out the master plan of the territory. |